Jackson Boulevard Reconstruction (Phases 1)

  • Architect: South Dakota DOT, City of Rapid City
  • Division Manager: Dave Dailey
  • Project Manager: Sean Hogard
  • Superintendent: Brandt Headquist, Rich Harmon, Tom Harmon, Dale Mogensen, Keith Hart, Roger Jensen
  • Owner: South Dakota DOT, City of Rapid City
  • Subcontractors: Arleth Land Surveying, Complete Concrete, J.H. Hilt Engineering, Inc., J.V. Bailey Co. Inc., Loren Doyle Concrete, Inc., M&M Fencing, Inc., Midwest Marketing, LLC, Muth Electirc, Inc., Pat Meier Trucking, Simon Contractors of South Dakota, Inc., Traffic Services Company
  • Self Work: Utilities, Water, Sanitary, Storm, Grading, PCC Paving, Sidewalk, Curb and gutter

Stretching from Mountain View Road to Sheridan Lake Road, this portion of Jackson Boulevard proved to be quite a challenge. With over ## businesses along this project our number one priority was maintaining access to these businesses for the general public.