Main Street (Sturgis, SD)

  • Architect: Four Front Design
  • Division Manager: Dave Dailey
  • Project Manager: Jason Brandsted
  • Superintendent: Bret Olson
  • Owner: City of Sturgis, SD; SD DOT
  • Size: $4,051,048.13
  • Subcontractors: P.I.E, Sacrison Paving, Traffic Services Company, Rockingtree Landscape, Broze Engineering, Midstate Reclamation, Timber Ridge Construction, Franks Tree Service, Double H Masonry
  • Self Work: Installation of water main, storm sewer, all concrete work, and all grading and base course work.

This 5 block urban reconstruction project through Main Street in Sturgis, SD involves a new water main, reconfigured storm sewer, new curb and gutter, decorative sidewalk and crosswalks, decorative light poles, landscaping and irrigation, and asphalt pavement.