Lead-Deadwood Elementary School Renovation

  • Architect: JLG; Construction Manager: ICS
  • Division Manager: Bob H
  • Project Manager: Dan W
  • Superintendent: Jack R
  • Owner: Lead-Deadwood school district
  • Size: 3.8 Million
  • Subcontractors: All Metal MFR, Low Roofing, Dakota Sealants, Hagen Glass, Ceramic Designs, Midwest, Advanced Builders, Hills Interiors, Kassure Painting, Rapid Fire Protection, Streamline Plumbing, Hermy’s Heating and Cooling, Freeman Electric.
  • Self Work: Demolition, CAT opening, install Lintels for HVAC and doors, framing, assemble and set lockers, install marker boards, tack boards, bath partitions, doors and hardware, set cabinets, and bathroom accessories.

Gut and Rebuild in two phases 12 weeks each during summer school closure.